There is no single order deadline for holiday displays. The timing depends on your in-store date, your destination, the material, the structure and how many sample rounds the design needs. That said, many brands running a November holiday program on ocean freight start the process in late July to mid-August and work backwards from there. This page shows how that planning works, what the lead times roughly look like, and what may still be possible if your season already feels tight.
Your schedule starts with the retailer's dates, not the factory's
A display only earns its keep if it is on the floor at the same time as the merchandise it holds. In most retail programs, holiday merchandise reaches the retailer's distribution center before the store set date, and store sets happen before the selling period starts. Those cut-off dates are set by the retailer, and they differ by retailer, category and country — which is why they should come from your retail or sales team rather than from a supplier.
The practical consequence is simple: the shipment needs to arrive early enough for receiving, distribution and store setup before the planned in-store date. That is why the useful question is not "when can the factory deliver?" but "when does the retailer need it, and what has to happen before then?"
Working backwards: lead times as planning estimates
The figures below are planning estimates for custom displays made in China, not commitments. They vary with structure, quantity, finishing, factory capacity and season — and metal fixtures generally run longer than corrugated ones.
Design and sampling
|
Step |
Planning estimate |
|
Structural design and quoting |
3–7 days after specs are confirmed |
|
Sample production |
typically 3–7 business days |
|
International sample delivery |
typically 3–7 days |
|
Sample review, revisions, second round |
5–15 days, depending on how many rounds are needed |
Production
|
Material |
Planning estimate |
|
Corrugated displays |
typically 20–30 days |
|
PVC / plastic displays |
approximately 25–40 days |
|
Metal fixtures |
approximately 30–50 days |
Freight and destination
|
Step |
Planning estimate |
|
Inland transport, booking, loading at port |
3–7 days, varies by location and season |
|
Ocean transit, China to US West Coast |
indicative port-to-port transit 18–25 days |
|
Ocean transit, China to US East Coast |
indicative port-to-port transit 28–40 days |
|
Ocean transit, China to Northern Europe |
indicative port-to-port transit 30–40 days |
|
Customs clearance and delivery to your DC |
depends on destination, customs and trucking — allow roughly 5–10 days |
|
DC to store distribution |
controlled by you or the retailer; not part of a supplier's lead time |
Ocean transit figures are indicative port-to-port estimates, not guaranteed delivery times. Actual transit varies with carrier, routing, port congestion and season.
As a planning starting point, a straightforward new corrugated display project — one sample round, no lighting, no unusual assembly — can often require around 12–16 weeks from the initial brief to arrival at the destination DC. Treat that as planning guidance rather than a standard rule. Complex structures, multiple sample rounds, peak-season booking, longer shipping routes and retailer-controlled distribution can all extend it, and retailer distribution happens after the DC date, so it sits on top of the timeline if you are working back from an in-store date.
Take a program with an early-November in-store date as an illustration. If the container needs to reach the DC in mid-October and port-to-port transit is around three weeks, the sailing points to mid-to-late September, production points to the first half of August, sample approval to July, and the brief to mid-July or earlier. Change any input — a later in-store date, a shorter route, a simpler structure, more production capacity — and every downstream date moves. The point of the example is the method, not the specific weeks.
Four common places where schedules can slip
Many display programs lose time before production even starts — during approvals, revisions and scheduling decisions.
If your season already looks tight
Starting in September does not automatically rule out ocean freight, but for an early-November in-store date it may already be very tight. Whether it is still achievable depends on the project itself — structure, material, finishing — plus the destination and the in-store date the retailer has given you. Rather than guess from a calendar, ask for a feasibility check against those inputs. Options that often help:
What to include when you ask for a quote
Lead times can only be confirmed against a real specification. When you request pricing, send your in-store date, your store count or door list, the product's dimensions and weight, the display quantity you need, and the destination — city or port and country. Add print and finish requirements, whether displays must ship flat-packed, and whether you want to buy on FOB or DDP terms. With those answers, a supplier can work backwards and build a realistic project schedule, and tell you which parts of it still have room and which do not.
If your season is tight, send us your in-store date and door list along with the details above, and we will tell you plainly what is achievable and what is not. We make corrugated cardboard displays and PVC folding displays that ship flat and assemble without tools, which can help reduce freight volume and simplify store setup. Get in touch with your dates and we will map the schedule for you.